What They Don't Tell You About Asbestos When Renovating a Pre-War Co-Op in NYC

Read as we reveal the hidden asbestos realities behind pre-war co-op walls - and the proactive planning process that keeps renovations on schedule.

March 23, 2026

|

8
mins to read
Interior at 801 West End Avenue, an Upper West Side pre-war co-op renovation by Gallery KBNY

What They Don't Tell You About Asbestos When Renovating a Pre-War Co-Op in NYC

What they don't tell you about pre-war co-op renovations in NYC: hidden asbestos. Gallery KBNY explains the proactive process that protects timelines and budgets.

In nearly every pre-war co-op gut renovation Gallery KBNY undertakes across Manhattan, asbestos is found not typically on walls or floors, where standard testing typically produces negative results, but behind them: wrapped around steam risers, insulating branch heating lines, and concealed within the mechanical infrastructure that pre-war buildings have relied on for a century.

For homeowners planning a gut renovation in a Manhattan pre-war co-op, understanding this reality, and knowing what a proactive firm does about it, is often the difference between a renovation that stays on schedule and on budget and one that doesn't.

About Gallery KBNY

Gallery KBNY is an award-winning, full-service design-build firm specializing in the architecture, interior design, and renovation of apartments, co-ops, condominiums, townhomes, and lofts across Manhattan and Brooklyn. Our integrated team of architects, designers, contractors, and project managers — with a founding partner involved in every project — manages every phase from board approvals and DOB permitting through design and construction. Because architecture, design, permitting, and construction are coordinated under one roof, the process remains streamlined, accountable, and transparent from start to finish. Our work has been recognized by Forbes, The New York Times, Architectural Digest, and Inc., and we have received Houzz Best of Design & Service seven consecutive years, along with 100+ five-star client reviews.

Below, we explain where asbestos is actually found in pre-war Manhattan co-ops, how an experienced design-build firm plans for it proactively, and what happens when an HVAC decision (seemingly unrelated to asbestos) triggers an abatement requirement with six-figure budget consequences if you're not prepared.

Table of Contents

[#1]Where Asbestos Actually Hides In New York City Pre-War Co-Ops[#1]

In pre-war Manhattan co-ops, asbestos is rarely found where most people expect it. Surface testing of walls and floors, the standard first-pass inspection, frequently returns negative results. The actual problem lies behind the walls.

The most common locations for asbestos in pre-war co-op apartments include:

Steam Risers

The vertical pipes that carry heat throughout pre-war buildings were routinely insulated with asbestos-containing materials. These risers run behind walls throughout the apartment and are rarely disturbed, until a renovation requires access.

Branch Heating Lines

The horizontal pipes that branch off from risers to deliver heat to individual rooms were similarly insulated. In a full gut renovation, these branch lines are almost always exposed and frequently require upgrading.

Pipe Elbows And Fittings

Joints, elbows, and valve connections on steam piping were often wrapped with asbestos-containing insulation and joint compound.

Boiler Room And Mechanical Equipment

In many pre-war buildings, boiler insulation and mechanical equipment casings contain asbestos, relevant when riser replacement requires coordination with building systems.

Flooring Adhesive

Black mastic adhesive used beneath original flooring tiles frequently contains asbestos, even when the tiles themselves test negative.

Plaster And Joint Compound

Some pre-war plaster formulations and mid-century joint compounds contain asbestos, though this is less common than pipe insulation issues.

The critical distinction: while surface-level asbestos tests may come back clean, a gut renovation that opens walls, especially in buildings with original steam heat, will almost certainly encounter asbestos-containing materials around the mechanical infrastructure.

[#2]Why Standard Asbestos Testing Misses the Problem[#2]

A standard pre-renovation asbestos inspection covers the visible, accessible surfaces of an apartment: walls, floors, ceilings, window caulking, and radiator covers. In most pre-war co-ops, these surface tests return negative or limited results — and homeowners can reasonably conclude that asbestos is not a significant concern.

That conclusion is usually wrong.

The mechanical infrastructure of a pre-war building (the steam risers, the branch lines, the distribution plumbing) runs inside the walls. It is not accessible during a standard surface inspection. And in renovation projects that include heating upgrades, HVAC installations, or any scope of work that requires opening walls near these systems, that infrastructure will be disturbed.

By the time a contractor discovers asbestos behind a wall mid-construction, the options narrow significantly: work stops, an emergency abatement contractor must be engaged, new competitive pricing is difficult to obtain, and the project timeline absorbs an unplanned delay of two to six weeks.

The alternative, proactive identification before demolition begins, is how experienced design-build firms protect both the budget and the schedule.

Kitchen at 91 Central Park West, a Manhattan pre-war co-op renovation by Gallery KBNY
Kitchen from Manhattan apartment renovation in 91 Central Park West.

[#3]The Proactive Process: How Gallery KBNY Handles It[#3]

On Gallery KBNY projects in pre-war co-op buildings, we assume asbestos is present behind the walls around the plumbing risers and heating lines from day one. We do not wait for a surface test to confirm this assumption. Our process follows a deliberate sequence:

Step 1: Probe & Open On Day One

At the start of a pre-war renovation, our team probes and selectively opens wall sections near risers and branch heating lines before demolition proceeds. This controlled opening gives our asbestos testing contractor access to the materials that matter (the insulation wrapping the pipes) rather than just the walls and floors.

Step 2: Document Immediately

Even when asbestos is visually apparent and likely, we document everything. We engage an accredited asbestos inspector to formally test and classify the materials. This documentation protects the client, ensures regulatory compliance, and creates the paper trail required for NYC Department of Buildings permitting.

Step 3: Obtain Multiple Abatement Proposals

Once asbestos is confirmed, we bring in multiple licensed abatement contractors to assess the scope and provide competitive pricing. This is a critical step that reactive processes skip: when asbestos is discovered mid-construction, the ability to competitively bid the abatement is lost. By engaging multiple contractors before construction begins, clients receive fair market pricing for the abatement work.

Step 4: Sequence Abatement Into The Project Timeline

With abatement scoped, contracted, and scheduled before demolition begins, the work is integrated into the construction sequence rather than interrupting it. The heating system upgrade (which is often the reason access is needed in the first place) proceeds on schedule.

The result: asbestos, in a pre-war co-op renovation, is not a surprise. It is a planned line item.

[#4]When HVAC Decisions Trigger Asbestos: A Real Case Study[#4]

Not every asbestos encounter in a pre-war co-op renovation is straightforwardly tied to a visible heating system upgrade. Sometimes, an HVAC decision that appears unrelated to asbestos sets off a chain of consequences that significantly affects both the budget and the project scope.

The following is based on an actual Gallery KBNY project in a pre-war Manhattan co-op.

The Situation

The building permitted central air conditioning, and the client had two options for their HVAC system:

Option 1: Ducted Central Air

Tue central HVAC, generally considered the superior residential system, delivering consistent temperature control throughout the apartment.

Option 2: Through-Wall PTAC Units

Individual packaged terminal air conditioners installed through wall cutouts, a common solution in older Manhattan buildings that lack the ductwork infrastructure for a full central system.

On paper, ducted central air was the better choice. In practice, however, the through-wall PTAC installation was what proceeded...and the reason had nothing to do with personal preference or aesthetic considerations.

The Problem: Electrical Capacity

The previous owner of the apartment had upgraded the electrical service to 100 amps. That upgrade, however, had been performed with incorrect wire conduit, a code-compliant labeling that masked an effective capacity of only 80 amps.

A ducted central HVAC system would have pushed the apartment's electrical load over that 80-amp effective capacity. To support it, a full electrical service upgrade would have been required, which is not a simple panel swap, but a complete service run from the basement of the building to the apartment.

In a pre-war co-op, that basement-to-apartment electrical service upgrade carries significant cost: close to six figures in this building, given the distance involved, the co-op's building requirements, and the labor required to run new conduit through a structure with no existing pathway.

The Through-Wall PTAC Decision And Its Own Asbestos Trigger

The through-wall PTAC installation (the option that avoided the electrical service upgrade) created its own asbestos consequence. Installing PTAC units requires cutting through the exterior walls of the building. In pre-war construction, those wall assemblies often contain asbestos-bearing materials in the insulation layers.

The through-wall cutouts triggered their own asbestos testing and abatement requirement. It was a smaller-scale abatement than a full riser replacement, but it was still a scope item that required proper testing, contractor engagement, and regulatory documentation.

The decision-making sequence illustrates precisely the kind of cascading consequence that experienced design-build firms surface during pre-construction planning and that clients working with separate consultants frequently encounter mid-construction.

Entry at 1035 Fifth Avenue, a Manhattan pre-war co-op renovation by Gallery KBNY
Entry from our full renovation of pre-war co-op in Manhattan at 1035 5th Avenue.

[#5]The Hidden Connection Between Electrical Capacity and HVAC Choice[#5]

The case study above illustrates a dynamic that surfaces regularly in pre-war co-op renovations: HVAC decisions are not independent choices. They interact with electrical capacity, building systems, co-op requirements, and — as demonstrated — asbestos abatement obligations in ways that can substantially alter the project budget.

Here is how those connections typically manifest in pre-war Manhattan co-op renovations:

The Five Constraints That Determine HVAC Choice

In a pre-war co-op, the best HVAC system is rarely determined by performance preference alone. Five constraints govern the decision. Here is how each HVAC option performs against each one.

How ducted central HVAC and through-wall PTAC perform against the five constraints that govern HVAC choice in a pre-war Manhattan co-op renovation.
Constraint Ducted Central HVACSuperior on paper Through-Wall PTACCommon pre-war workaround
01 Electrical Capacity Higher load draw. Often exceeds the effective amperage of pre-war service even when the panel is labeled at a higher capacity. May trigger a basement-to-apartment service upgrade. Lower per-unit load distributed across multiple circuits. Typically fits within existing service capacity without a building-side upgrade.
02 Building Permissions Many pre-war buildings restrict ductwork through shared walls or shaftway use. House rules often dictate where ducts can and cannot run. Generally permitted in buildings that allow exterior facade penetrations. Some landmark and historic-district buildings restrict visible exterior changes.
03 Construction Feasibility Requires opening walls and ceilings near risers and branch lines to run ductwork. High likelihood of asbestos exposure in the mechanical infrastructure. Requires cutting through exterior wall assemblies. Pre-war exterior walls frequently contain asbestos-bearing insulation, triggering a separate abatement scope.
04 Co-Op Board Requirements Significant ductwork scope often requires engineer sign-off, sound-attenuation specs, and may slow board approval. More documentation, more review rounds. Often pre-approved by building precedent. Smaller submission package. Faster path through the board, particularly in buildings where PTACs are already standard.
05 Budget Impact Hard cost of equipment, plus potential electrical service upgrade (approaching six figures in some pre-war buildings), plus asbestos abatement around the riser network. Lower equipment cost, no service upgrade, smaller-scope asbestos abatement contained to the wall cutouts. Total budget impact typically significantly lower.

The planning insight: Both options exist in every pre-war co-op renovation, and the right choice is rarely the one that looks superior on paper. The decision is the intersection of all five constraints, only fully visible during a thorough pre-construction evaluation.

The key planning insight: in a pre-war co-op, the 'best' HVAC system is rarely determined by performance preference alone. It is determined by the intersection of electrical capacity, building permissions, construction feasibility, co-op board requirements, and budget - and that intersection is only clearly visible during a thorough pre-construction evaluation.

HVAC-To-Asbestos Decision Cascade

In a pre-war co-op, HVAC choice is rarely independent. Each option triggers a cascade through electrical capacity, wall penetration, and abatement scope. Here is how the two most common paths actually unfold.

Path A

Ducted Central HVAC

Stage 01

HVAC Choice

Ducted central air. Superior performance on paper.

>

Stage 02

Electrical Load Check

Verify actual amperage, not labeled. Many pre-war apartments have effective capacity below name plate.

>

Stage 03

Service Upgrade Required

If load exceeds capacity, basement-to-apartment service run. Approaches six figures in some buildings.

The planning insight: Neither path is asbestos-free. The right HVAC choice depends on the intersection of electrical capacity, wall composition, board permissions, and budget, all of which are only visible during a thorough pre-construction evaluation, not at design selection.

[#6]Budget Implications: What to Plan For[#6]

Asbestos-related costs in a pre-war co-op renovation fall into several categories, each of which should be addressed as a discrete line item in the project budget during pre-construction planning.

How A Single Abatement Compounds Into A Six-Figure Surprise

The base abatement cost exists in both scenarios. What changes is what gets layered on top when it is found mid-construction. Same $10,000 of underlying abatement work, two very different totals.

Scenario A

Proactive: Abatement Scoped Before Demolition

Base abatement (typical scope, competitive bid) $10,000
Emergency procurement premium $0
Extended temporary housing $0
Trade re-mobilization & re-sequencing $0
Total Asbestos-Related Cost $10,000
Scenario B

Reactive: Same Asbestos, Discovered Mid-Demolition

Base abatement (typical scope, emergency single bid) $10,000
Emergency procurement premium (+30 to 50%) +$4,000
Extended temporary housing (3 added weeks at Manhattan rates) +$15,000
Trade re-mobilization & re-sequencing +$10,000
Total Asbestos-Related Cost $39,000

Cost Differential, Same Abatement Scope

~ 4x more expensive when reactive

The compounding math: Reactive discovery does not just add the abatement cost. It adds an emergency pricing premium on the abatement itself, weeks of additional temporary housing, and the cost of de-mobilizing and re-mobilizing trades who had already started work. The base cost is the same. Everything stacked on top is avoidable.

A thorough pre-construction investigation (including probing walls near mechanical systems, obtaining competitive abatement proposals, and evaluating the electrical implications of HVAC choices) can convert these figures from reactive surprises into planned budget line items. Learn more about the costs of a complete gut renovation of a pre-war co-op in NYC.

Asbestos-Related Budget Line Items

Every asbestos-related cost in a pre-war Manhattan co-op renovation, mapped to a budget category with current 2026 ranges. Use this as a planning reference during pre-construction.

Asbestos budget line items for pre-war NYC co-op renovations, with cost ranges and the project phase each cost belongs to.
Line Item Cost Range When & Why
Required Documentation ACP-5 Clearance Testing $1,500 to $4,000 depending on sample count Required by NYC DOB before a renovation permit can be issued. Covers accredited inspection and sample lab analysis.
Hard Cost Typical-Scope Abatement $3,000 to $15,000+ localized pipe insulation or floor mastic Limited scopes: a few linear feet of pipe wrap, isolated pipe fittings, or a single room of flooring adhesive. Most pre-war renovations fall in this band.
Hard Cost Extensive-Scope Abatement $15,000 to $40,000+ full riser or branch line replacement Full vertical riser replacement, multiple branch heating lines, or whole-apartment mastic abatement under original flooring. Common in full gut renovations.
Avoidable Premium Mid-Construction Discovery +30 to 50% above proactive market rate When asbestos is found mid-demo, competitive bidding is no longer practical. Single-bid emergency procurement adds a premium of 30 to 50 percent over proactively planned abatement.
Indirect Cost Temporary Housing Impact $5,000 to $15,000+ per month, Manhattan rates Proactive planning sequences abatement into the existing demo window, no incremental displacement. Reactive discovery adds 2 to 6 weeks of housing cost.

Gallery KBNY ReferenceRanges reflect 2026 NYC market conditions on pre-war Manhattan co-op renovations. Estimates that omit any of these line items are incomplete.

How to plan with this: Each row is a line item that belongs in your pre-construction budget. Treating any of them as a contingency rather than a planned cost is the structural reason mid-construction surprises happen in pre-war renovations.

[#7]Timeline: How Proactive Planning Protects Your Schedule[#7]

Asbestos discovery mid-construction is one of the most common causes of unplanned project delays in pre-war Manhattan co-op renovations. Understanding how proactive planning changes the timeline math is essential for setting realistic expectations.

Where The 2 To 6 Weeks Of Delay Actually Come From

When asbestos is found mid-demolition, the delay is not one event. It is four sequential phases, each with its own duration. Here is the math.

  1. 01

    Phase 01

    Work Stop & Site Containment

    All trades pull back from the affected area. Site is contained per NYC DEP requirements. DOB notification filed if applicable.

    Added Time

    3 to 5 days

  2. 02

    Phase 02

    Testing, Classification, Abatement Procurement

    Accredited inspector tests and classifies materials. Without time to bid competitively, a single licensed abatement contractor is engaged on emergency timing.

    Added Time

    1 to 2 weeks

  3. 03

    Phase 03

    Abatement & Clearance Inspection

    Licensed abatement performed under containment. Post-abatement air sampling and visual clearance inspection by independent inspector before work can resume.

    Added Time

    1 to 2 weeks

  4. 04

    Phase 04

    Trade Re-Mobilization

    Trades who were pulled off site need to be rebooked into their schedules. Sequencing reset. Some trades cannot re-mobilize immediately, adding gap time before construction resumes.

    Added Time

    3 days to 2 weeks

The Math
Site stop + Testing + Abatement + Re-mobilization

Total Schedule Impact
2 to 6 weeks

What the math reveals: The abatement work itself is only part of the delay. Site containment, emergency procurement, and trade re-mobilization compound on top. Proactive planning compresses all four phases into the pre-construction window, where they do not affect the construction schedule at all.

The proactive approach does not eliminate the cost of asbestos abatement, that cost exists regardless. What it eliminates is the schedule impact, the emergency pricing premium, and the cascade of delays that follows an unplanned mid-construction stop.

[#8]Choosing a Design-Build Firm That Understands Pre-War Realities[#8]

The practical value of an experienced design-build firm in a pre-war co-op renovation is not measured in design aesthetics alone. It is measured in the ability to anticipate what lies behind the walls and to plan for it before it becomes a problem.

When evaluating firms for a pre-war Manhattan co-op renovation, the following questions are worth asking directly:

Do You Assume Asbestos Is Present In Pre-War Mechanical Systems, And Do You Plan For It From Day One?

A firm experienced in pre-war co-ops will not rely solely on surface test results. They will probe selectively before demolition begins and engage abatement contractors during the pre-construction phase, not after demolition uncovers the problem.

How Do You Evaluate HVAC Options Against Electrical Capacity Before Presenting Them To A Client?

HVAC choice in a pre-war co-op is not a standalone decision. An experienced firm evaluates the electrical service capacity (including verifying whether labeled amperage reflects actual capacity) before recommending a system. In some buildings, the 'best' HVAC system on paper is not the best system for the specific building and budget.

Do You Obtain Multiple Abatement Proposals Before Construction Begins?

Competitive bidding for abatement work is only possible during the pre-construction phase. A firm that identifies asbestos in advance and brings in multiple licensed contractors for pricing is providing a direct cost benefit to the client. Emergency single-bid abatement procurement is significantly more expensive.

Is Board Approval, Permitting, And ACP-5 Documentation Managed In-house?

NYC DOB requires an ACP-5 or ACP-21 certificate before a renovation permit can be issued. A design-build firm that manages this documentation as part of the permitting process, rather than passing it to the client to coordinate separately, eliminates a common source of permit delays.

A design-build approach integrates architecture, interior design, board approvals, permitting, and construction under a single coordinated team. In pre-war co-op buildings, where regulatory requirements and hidden conditions interact at every phase, this integration is particularly valuable.

Interior at 801 West End Avenue, an Upper West Side pre-war co-op renovation by Gallery KBNY

[#9]Frequently Asked Questions[#9]

Does Every Pre-War Co-Op In NYC Have Asbestos?

Not every pre-war co-op contains asbestos, but the probability is high enough that experienced renovation firms treat its presence as an assumption rather than a question. Surface tests — which cover walls, floors, and ceilings — often return negative results. The actual risk in pre-war co-ops lies in the mechanical infrastructure behind the walls: steam riser insulation, branch heating line wrapping, pipe fittings, and elbows. In Gallery KBNY's experience renovating pre-war co-ops across Manhattan, encountering asbestos in these locations during a gut renovation is the rule, not the exception. The important variable is not whether asbestos is present, but whether the renovation team is prepared for it before construction begins.

What Does Asbestos Abatement Cost In A Pre-War NYC Apartment Renovation?

Asbestos abatement costs in a pre-war NYC apartment renovation typically range from $3,000–$10,000 for limited scopes involving localized pipe insulation or flooring adhesive, and from $10,000–$40,000+ for more extensive work such as full riser replacement or significant branch line abatement. Required ACP-5 clearance testing adds $1,500–$4,000 to the project, and is required by NYC DOB before a renovation permit can be issued. Homeowners who plan for abatement in the pre-construction phase — obtaining multiple competitive bids before demolition begins — typically pay market rates. Those who discover asbestos mid-construction typically pay an emergency premium of 30–50% above market because competitive bidding is no longer practical.

Can An HVAC Decision Trigger Asbestos Abatement In A Pre-War Co-Op?

Yes. HVAC installations that require penetrating or opening walls in pre-war co-op buildings can disturb asbestos-containing materials and trigger an abatement requirement. Through-wall PTAC unit installations, for example, require cutting through the building's exterior wall assembly — which in pre-war construction often contains asbestos insulation. Ducted central HVAC systems require opening walls near risers and branch lines to run ductwork. Either path may require asbestos testing and abatement depending on the materials present. The interaction between HVAC choice, electrical capacity, and asbestos scope is one of the more complex budget variables in pre-war co-op renovations — and one that only surfaces with thorough pre-construction planning.

What Is An ACP-5 Certificate And Why Is It Required For NYC Renovations?

An ACP-5 (Asbestos Control Program Form 5) is a clearance certificate issued by a licensed asbestos inspector confirming that a renovation area has been tested for asbestos and either found to be free of asbestos-containing materials or properly abated. NYC DOB requires an ACP-5 certificate before issuing a renovation permit for work that involves demolition or disturbance of building materials in pre-1987 buildings. In practical terms, this means that any gut renovation in a pre-war Manhattan co-op requires ACP-5 documentation as a standard step in the permitting process. The cost ranges from $1,500–$4,000 depending on the scope of testing required.

What Happens If Asbestos Is Discovered During Construction In A NYC Renovation?

If asbestos-containing materials are discovered after construction has begun, work must stop in the affected area until the materials are tested, classified, and properly abated by a licensed NYC asbestos abatement contractor. This typically results in an unplanned construction delay of two to six weeks while the abatement contractor is engaged, testing and documentation are completed, abatement is performed, and a clearance inspection is passed before work can resume. In addition to the delay, emergency abatement procurement — without the benefit of competitive bidding — typically carries a cost premium of 30–50% over proactively planned abatement. This is why experienced design-build firms proactively investigate and plan for asbestos before demolition begins.

How Does Electrical Capacity Affect HVAC Choice In A Pre-War Co-Op Renovation?

Electrical capacity is one of the most frequently overlooked constraints in pre-war co-op HVAC planning. Many pre-war Manhattan co-op apartments operate on electrical service that was upgraded decades ago — but that upgrade may not reflect actual usable capacity. In one Gallery KBNY project, an apartment labeled as 100-amp service was effectively running at 80 amps due to incorrect conduit used in the prior upgrade. Adding a ducted central HVAC system would have exceeded that capacity, requiring a full electrical service run from the basement — an upgrade that approached six figures in that building. Through-wall PTAC units, while less ideal from a performance standpoint, eliminated the electrical upgrade requirement. Evaluating actual electrical capacity — not labeled capacity — before selecting an HVAC system is a critical pre-construction step in pre-war co-op renovations.

Do I Need To Vacate My Apartment During Asbestos Abatement?

Yes. NYC DOB and EPA regulations require the evacuation of occupied areas during asbestos abatement. In a gut renovation, this typically coincides with the period when the apartment is already vacated for construction — so the abatement itself generally does not add incremental displacement time if it is proactively planned and sequenced into the demolition phase. If asbestos is discovered mid-construction and the abatement is reactive, however, the work stoppage and abatement period can extend the overall project timeline, which may affect temporary housing arrangements and associated costs. Temporary housing during a Manhattan co-op gut renovation typically ranges from $5,000–$15,000+ per month, making timeline protection a direct budget consideration.

How Do I Know If My Pre-War Co-op Building Has Asbestos Around The Risers?

The most reliable way to determine whether asbestos is present around the risers in a pre-war Manhattan co-op is to engage an accredited asbestos inspector to conduct targeted testing of the pipe insulation and fittings — not just the surface materials. Standard surface inspections often miss behind-wall mechanical insulation. Gallery KBNY's process involves probing and selectively opening wall sections near risers and branch heating lines at the start of a pre-war renovation project, before general demolition begins. This controlled access gives the asbestos inspector access to the materials that are most likely to contain asbestos, producing a more accurate picture of what the renovation will encounter — and allowing abatement to be planned proactively.

let’s

Design-Build

together

By providing your phone number, you agree to receive text messages from Gallery. Message and data rates may apply. Message frequency varies.

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form

Dynamic Image 1

About Gallery KBNY

Gallery KBNY is an award-winning, full-service design-build firm specializing in the architecture, interior design, and renovation of apartments, co-ops, condominiums, townhomes, and lofts across Manhattan and Brooklyn. Our integrated team of architects, designers, contractors, and project managers — with a founding partner involved in every project — manages every phase from board approvals and DOB permitting through design and construction. Because architecture, design, permitting, and construction are coordinated under one roof, the process remains streamlined, accountable, and transparent from start to finish. Our work has been recognized by Forbes, The New York Times, Architectural Digest, and Inc., and we have received Houzz Best of Design & Service seven consecutive years, along with 100+ five-star client reviews.

Dynamic Image 2

Pre-War Co-Op Renovation Asbestos: Key Facts (2026)
TopicKey Detail
Where asbestos is typically foundBehind walls — pipe insulation, steam risers, branch heating lines
Surface test resultsOften negative on walls and floors — hidden asbestos requires invasive investigation
Required NYC testingACP-5 clearance certificate required before DOB permit filing
ACP-5 testing cost$1,500–$4,000 depending on scope and number of samples
Abatement cost — typical scope$3,000–$15,000+ depending on linear footage and materials
Abatement cost — extensive scope$15,000–$40,000+ for full riser or branch line replacement
Timeline impact — proactive planningMinimal — when abatement is scoped and contracted in pre-construction
Timeline impact — reactive discovery2–6 weeks of unexpected delay mid-construction
Buildings most affectedPre-war co-ops built before 1940; especially those with original steam heat

Source: Gallery KBNY pre-war co-op renovation project data (2026)

Managing Partner/CEO

Avi Zikry

Avi Zikry is the CEO and managing partner of Gallery KBNY, a full service design-build firm specializing in the design and interior renovation of apartments, townhomes, and lofts in NYC. Under his leadership, Gallery KBNY has earned the reputation for delivering exceptional service and beautiful homes to our select group of clients. Avi's strategic positioning extends beyond the brand. He has strategically cultivated a network of industry partners and suppliers, forging strong alliances that allow Gallery KBNY to access cutting-edge technologies and materials. By staying abreast of industry trends and technological advancements, Avi ensures the firm remains at the forefront of innovation, consistently offering clients the latest design solutions and construction methodologies.